Clearing out the Front of the School

Today the crew was hard at work at clearing out the space in front of the school (where the front lobbies will be brought out 10 feet, and where there'll be a covered porch on the left and the right). They removed all of the broken up concrete from yesterday, the final bushes in front of Blue and Turquoise Rooms, and a lot of dirt and mulch. It looks like it's getting closer to being ready to pour concrete!
Over on in the main field, dump trucks arrived to haul off all of the unwanted material, and it looks like they are working on burying the newly-placed sewer line. Hopefully this means that the construction crew will soon be able to park in the back field, freeing up our always-needed parking spaces! :)